Systems integration: is automation worth it?

Level: Advanced 11 min read 46 questions

Integrating an automation system means getting machines, sensors, robots and programs to work as a whole. But before the how comes a question many technicians never ask: is it worth it for the company? A badly chosen automation project can cost a lot of money and improve nothing. Being able to analyse it with numbers is what turns a good technician into someone whose opinion is asked before anything is bought.

First, measure: you do not automate by eye

Before proposing anything, you need to know how the process works today. The minimum data:

From the demand you calculate the takt time, the pace at which you must produce to meet it:

takt time = available time / parts demanded

Example: a shift with 7.5 productive hours has 27,000 seconds. If 900 parts must be made per shift, the takt time is 27,000 / 900 = 30 s. Any station that takes more than 30 s per part makes it impossible to meet demand.

The bottleneck

A line with several stations in a row produces at the pace of its slowest station. That station is the bottleneck, and it sets the pace.

Station 1 20 s Station 2 35 s Station 3 25 s Station 4 22 s bottleneck The line makes one part every 35 s, even though the other stations are faster.
The slowest station sets the pace of the whole line. Improving any other station does not increase output.

Two very practical conclusions follow from this:

More parts are only worth it if they sellIncreasing capacity is only a saving if there is demand for those parts. If the company already makes everything it sells, the value of automation has to come from somewhere else: fewer people on hard tasks, fewer rejects or fewer injuries.

OEE: how much a machine really delivers

OEE (overall equipment effectiveness) sums up in one number how much of what a machine could produce it really produces. It is calculated by multiplying three factors:

OEE = availability × performance × quality

A complete example

An 8-hour shift (480 min) with 30 minutes of planned breaks leaves 450 min of planned production time. There were 45 min of stoppages, so the machine ran for 405 min. Its ideal cycle is 30 s per part: in 405 min (24,300 s) it could have made 810 parts, but it made 680. Of those, 660 were good.

Quick check: the 660 good parts, at 30 s each, are worth 330 min of perfect work. 330 / 450 ≈ 73 %. Same result.

Planned time: 450 min Running: 405 min At ideal rate: 340 min Good parts: 330 min − 45 min of stoppages − 65 min slow running, minor stops − 10 min of bad parts OEE = 330 / 450 ≈ 73 %
OEE as a waterfall: each factor shows where the time is lost. Here, the biggest loss is performance, not stoppages.

85 % is often quoted as world class, and many factories are well below it. But the usefulness of OEE is not comparing yourself with others: it is knowing where the losses are. In the example, the biggest loss is in performance: minor stops and slow running. It might be fixed with a badly adjusted sensor or a recurring jam, without buying anything. If the loss were in availability because of long changeovers, the solution might be to organise those changeovers better, not a robot.

When automation pays off

When it does not pay off, or not yet

The numbers: investment and return

The calculation looks simple, but it is often done badly because costs are forgotten and savings are inflated.

What it really costs

Not just the machine: engineering, installation, safety guarding (fencing, light curtains, interlocks), programming, commissioning, staff training, spare parts, annual maintenance and the production lost while it is being installed.

What it really saves

Labour hours (at their full cost to the company, not take-home pay), fewer rejects, extra capacity if there is demand, and fewer injuries. An important point: labour savings are only real if those hours stop being paid or are put to other useful work.

The payback period

payback period = total investment / net annual saving

An example with made-up round figures: a palletising cell with a total investment of €120,000. It frees one operator on each of two shifts, at €30,000 a year each in cost to the company: €60,000. It cuts rejects from knocks by €6,000 a year. Its maintenance costs €6,000 a year. Net saving: 60,000 + 6,000 − 6,000 = €60,000 a year. Payback period: 120,000 / 60,000 = 2 years.

Industrial companies often ask for the investment to be recovered in two or three years, although it depends on the company. A proposal with honest numbers, including the costs others forget, inspires far more confidence than a spectacular saving.

Intermediate options

Between doing nothing and a fully automatic line there are many steps, often more profitable:

The technical side: getting machines to understand each other

When machines from different manufacturers are joined together, the critical point is the interface: which signals are exchanged and what each one means. A typical example between a machine that delivers parts and a robot that picks them up:

SignalSent byMeaning
Part availableMachineA part is ready at the pick-up position
Robot insideRobotThe robot is in the zone: the machine must not move
Part pickedRobotThe robot has taken the part and left the zone
FaultBothThe other equipment has an alarm that prevents it from continuing

This exchange of “request, response and confirmation” is called a handshake. For it to work well:

Before the system is signed off, acceptance tests are carried out: the FAT (factory acceptance test), at the builder’s workshop, and the SAT (site acceptance test), once installed at the customer’s plant.

Safety and CE marking: the most forgotten risk

In the European Union, every machine must carry the CE marking, and its manufacturer is responsible for assessing its risks, preparing the technical file, drawing up the declaration of conformity and writing the manual. The reference is the Machinery Directive 2006/42/EC, which Regulation (EU) 2023/1230 replaces from 20 January 2027. Outside the EU the rules differ: Great Britain, for example, has its own UKCA marking, and in the United States machine safety is governed by OSHA regulations and standards such as NFPA 79.

Typical mistakeQuoting for an integration without accounting for safety or CE marking. Fencing, light curtains, safety relays, the risk assessment and the documentation can be a significant part of the cost, and finding out at the end ruins the payback period.

This section is guidance, not legal advice: on each project, a safety manager or a CE marking expert must confirm which obligations apply.

Checklist before proposing an automation project

  1. Do I have real data on output, stoppages, rejects and cycle times?
  2. Do I know which station is the bottleneck and whether there is demand to produce more?
  3. What is the current OEE and where are the biggest losses: availability, performance or quality?
  4. Is the process stable, or does it need fixing first?
  5. Is there a cheaper intermediate option that solves most of the problem?
  6. Have I included every cost: engineering, safety, commissioning, training and maintenance?
  7. Are the savings real and calculated at full cost to the company?
  8. What is the payback period, and is it acceptable to the company?
  9. Is it clear who will be the manufacturer for CE marking purposes?
  10. Are there people who can maintain and troubleshoot the system?

Summary