ExamRobotic

OEE calculator

OEE (overall equipment effectiveness) sums up in one number how much of what a machine could produce it really produces. But the useful part is seeing where it is lost: in stoppages, in slow running or in bad parts. Enter the data for one shift and the calculator gives you the three factors and points to the biggest loss.

How it is calculated

Planned production time already excludes planned breaks, such as rest periods or shifts with no production. Downtime covers the unplanned stops and the ones you want to improve: breakdowns, changeovers, waiting for material.

Example

With the calculator’s default data: availability 405 / 450 = 90 %; performance 680 × 30 / (405 × 60) ≈ 84 %; quality 660 / 680 ≈ 97 %. OEE ≈ 73 %. The biggest loss is in performance: minor stops and slow running.

How to use the result

85 % is often quoted as world class, but what matters is the trend of your own machine and tackling the biggest loss first. Adjusting a sensor often gains more than buying a new machine.

Typical mistakeUsing the measured real cycle time as the ideal cycle time. Performance then always comes out close to 100 % and the slow-running losses stay hidden. The ideal cycle is the machine’s design cycle.